Construction of New Energy Centre, Castle Park
Construction of New Energy Centre Work Completed as a sub-contractor for Vital Energi
Location: Castle Park
CDM Role: Sub-Contractor for Vital Energi
Scope of Works Included:
- Constructed in an area of archaeological remains of the old castle
- Small site with limited working room which was logistically demanding
- Building close relations with archaeological teams to work through obstacles
- Removal of underground obstructions to support (UXO Team – unexploded ordinance)
- Construction of foundations for building – raft on pile cap
- Construction of abstraction plant pit to allow installation of a floating abstraction unit over harbour wall
- Construction of building
- Landscaping to completion